<?xml version="1.0" encoding="UTF-8"?>
<!DOCTYPE article PUBLIC "-//NLM//DTD JATS (Z39.96) Article Authoring DTD v1.4 20240229//EN" "JATS-articleauthoring1.dtd">
<article article-type="research-article" xml:lang="zh-CN" xmlns:xlink="http://www.w3.org/1999/xlink">
  <front>
    <journal-meta>
      <journal-id journal-id-type="publisher-id">58</journal-id>
      <journal-title-group>
        <journal-title>施工技术研究</journal-title>
        <abbrev-journal-title>Research on Construction Technology</abbrev-journal-title>
      </journal-title-group>
      <issn>ISSN: 3104-8129 EISSN: 3104-8137</issn>
      <publisher>
        <publisher-name>睿核出版社有限公司</publisher-name>
      </publisher>
    </journal-meta>
    <article-meta>
      <article-id pub-id-type="doi">10.65700/RHSGJSYJ01-2611-8129-0423</article-id>
      <article-id pub-id-type="publisher-id">16421</article-id>
      <title-group>
        <article-title>海外工业厂房项目招标阶段造价咨询与预算控制研究 ——以艾郎摩洛哥 MW 级叶片工厂建设项目为例</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>丁超</string-name>
        </contrib>
      </contrib-group>
      <pub-date pub-type="epub">
        <year>2026</year>
        <month>2</month>
      </pub-date>
      <issue>2</issue>
      <abstract>
        <p>海外工业厂房项目并非国内工业建设模式的简单外移，其成本的形成受属地法规、跨境采购、国际物流、税务政策、汇率结算、
清关效率及当地劳务组织等多种变量的叠加影响，而其招标阶段造价咨询需要由传统清单编制、控制价审核，转向合约结构、采购路径和
风险责任的前置策划。本文以艾郎摩洛哥 MW 级叶片工厂建设项目为例，结合超大跨度厂房、材料费用占比高、钢结构跨境供应和自贸区
免税报备等特点，分析如何通过合约架构拆分、目标成本分解、清单特征细化、免税清单管理、报价清标和风险条款闭环，将技术标准、
物流清关、税费条件和履约边界同步固化于招标文件。研究表明，海外工业厂房预算控制的关键不在于单项价格压降，而在于把不确定因
素转化为可报价、可评审、可追责的合同条件，从而降低施工阶段变更、索赔和资金占用风险。</p>