<?xml version="1.0" encoding="UTF-8"?>
<!DOCTYPE article PUBLIC "-//NLM//DTD JATS (Z39.96) Article Authoring DTD v1.4 20240229//EN" "JATS-articleauthoring1.dtd">
<article article-type="research-article" xml:lang="zh-CN" xmlns:xlink="http://www.w3.org/1999/xlink">
  <front>
    <journal-meta>
      <journal-id journal-id-type="publisher-id">58</journal-id>
      <journal-title-group>
        <journal-title>施工技术研究</journal-title>
        <abbrev-journal-title>Research on Construction Technology</abbrev-journal-title>
      </journal-title-group>
      <issn>ISSN: 3104-8129 EISSN: 3104-8137</issn>
      <publisher>
        <publisher-name>睿核出版社有限公司</publisher-name>
      </publisher>
    </journal-meta>
    <article-meta>
      <article-id pub-id-type="doi">10.65700/RHSGJSYJ01-2611-8129-0435</article-id>
      <article-id pub-id-type="publisher-id">16434</article-id>
      <title-group>
        <article-title>铝模快拆体系下现浇混凝土楼板开裂技术管理实践</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>沈曰代</string-name>
        </contrib>
      </contrib-group>
      <pub-date pub-type="epub">
        <year>2026</year>
        <month>2</month>
      </pub-date>
      <issue>2</issue>
      <abstract>
        <p>本文以山东济南章丘区山东外事职业大学科教园区项目 8 号楼学生宿舍为工程实例，探索解决铝模快拆体系下楼板开裂的解决
办法。本项目为高校民生工程，交付节点刚性固定，为提高施工质量楼座混凝土构件辅助成型措施采用铝模快拆体系，却因传统连续流水
施工，致使早期混凝土楼板承受上层施工荷载与模板扰动，引发严重楼板开裂质量风险。项目通过裂缝观测、成因系统排查、施工工序调
整、施工荷载封闭管控、铝模支撑体系优化、多方参建方协调、施工进度重新排布，形成完整的层间间隔施工管理措施，并通过 8 层传统
施工与 9 层优化施工对比试验验证治理成效。结果表明，该管理措施可有效控制楼板开裂风险，同时实现项目质量风险管控与工期按期履
约的双重平衡，为同类装配式模板体系施工质量管控提供实践参考。</p>