<?xml version="1.0" encoding="UTF-8"?>
<!DOCTYPE article PUBLIC "-//NLM//DTD JATS (Z39.96) Article Authoring DTD v1.4 20240229//EN" "JATS-articleauthoring1.dtd">
<article article-type="research-article" xml:lang="zh-CN" xmlns:xlink="http://www.w3.org/1999/xlink">
  <front>
    <journal-meta>
      <journal-id journal-id-type="publisher-id">58</journal-id>
      <journal-title-group>
        <journal-title>施工技术研究</journal-title>
        <abbrev-journal-title>Research on Construction Technology</abbrev-journal-title>
      </journal-title-group>
      <issn>ISSN: 3104-8129 EISSN: 3104-8137</issn>
      <publisher>
        <publisher-name>睿核出版社有限公司</publisher-name>
      </publisher>
    </journal-meta>
    <article-meta>
      <article-id pub-id-type="doi">10.65700/RHSGJSYJ01-2611-8129-0438</article-id>
      <article-id pub-id-type="publisher-id">16437</article-id>
      <title-group>
        <article-title>市政公路桥涵工程复杂环境施工技术与实践研究</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>肖勇</string-name>
        </contrib>
      </contrib-group>
      <pub-date pub-type="epub">
        <year>2026</year>
        <month>2</month>
      </pub-date>
      <issue>2</issue>
      <abstract>
        <p>随着城市化进程加速，市政公路桥涵工程面临的施工环境日趋复杂。本文以 G228 公路新建工程 6 标为依托，针对污水管埋深 7
米引发的超危大施工风险，以及三团港大桥 0#块上方 110kV 高压线导致的安全距离不足两大技术难题，开展了施工技术优化研究。通过将
原顶管井工艺变更为水平定向钻拖拉管井施工，采用拉森钢板桩围护与分级扩孔回拖技术，以及创新搭设钢管桩型钢拼装平台并结合液压
顶推移位技术实现挂篮安全安装，系统阐述了各项工艺的关键参数与操作要点。本工程实践和研究可为同类复杂环境下市政桥涵工程施工
提供技术参考。</p>
      </abstract>