        <journal-title>施工技术研究</journal-title>
        <abbrev-journal-title>Research on Construction Technology</abbrev-journal-title>
      </journal-title-group>
      <issn>ISSN: 3104-8129 EISSN: 3104-8137</issn>
      <publisher>
        <publisher-name>睿核出版社有限公司</publisher-name>
      </publisher>
    </journal-meta>
    <article-meta>
      <article-id pub-id-type="doi">10.65700/RHSGJSYJ01-2611-8129-0442</article-id>
      <article-id pub-id-type="publisher-id">16441</article-id>
      <title-group>
        <article-title>油气回收处理装置配套管道工程施工管理研究 ——以某石化技改项目为例</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>马树波</string-name>
        </contrib>
      </contrib-group>
      <pub-date pub-type="epub">
        <year>2026</year>
        <month>2</month>
      </pub-date>
      <issue>2</issue>
      <abstract>
        <p>中海壳牌石油化工有限公司在乙烯二期罐区新建一套油气回收处理装置 VRU，配套管道工程施工涉及大体积混凝土基础浇筑、
地脚螺栓安装、易燃易爆介质输送管道安装等难点问题。根据此项目，围绕研究管道工程施工管理问题，梳理工程情况及工程条件，分析
管道安装施工的三大管理难点：防止泄漏、法兰及静电接地可靠性保证、新旧装置相连口安全协调等；然后阐述从工程全过程开展质量控
制、特殊管道安装控制和协调管理等方面的具体措施。实践证明，所采取的措施保证了工程施工的安全和质量，可供类似石化技改的管道
工程借鉴。</p>